75-6905.Same; notice of bid with nonjudgmental mistake; basis for withdrawal. The bidder must notify the awarding authority within two business days after the bids have been opened that there is a nonjudgmental mistake in its bid. The awarding authority shall permit a bidder to withdraw its bid without penalty or forfeiture of bid security if:

(a) A nonjudgmental mistake is evident on the face of the bid; or

(b) the bidder establishes by clear and convincing evidence that a nonjudgmental mistake was made.

History: L. 1995, ch. 69, § 5; July 1.